1
GATE ME 2000
Subjective
+5
-0
Given below are the data for a project network. GATE ME 2000 Industrial Engineering - Pert and Cpm Question 2 English
(a) Draw the network for the above project capturing the precedence relationships.
(b) Find the critical path and its duration.
2
GATE ME 2000
MCQ (Single Correct Answer)
+2
-0.6
In a time series forecasting model, the demand for five time periods was $$10, 13,$$ $$15,$$ $$18$$ and $$22.$$ A linear regression fit resulted in an equation $$F = 6.9 + 2.9$$ $$t$$ where $$F$$ is the forecast for period $$t$$. The sum of absolute deviations for the five data is
A
$$2.2$$
B
$$0.2$$
C
$$-1.2$$
D
$$24.3$$
3
GATE ME 2000
MCQ (Single Correct Answer)
+2
-0.6
In a single server infinite population queuing model, arrivals follow a Poisson distribution with mean $$\lambda = 4$$ per hour. The service times are exponential with mean service time equal to $$12$$ minutes. The expected length of the queue will be
A
$$4$$
B
$$3.2$$
C
$$1.25$$
D
$$24.3$$
4
GATE ME 2000
Subjective
+5
-0
Solve the following linear programming problem by simplex method

$$\eqalign{ & Maximize\,\,\,\,\,\,4{x_1} + 6{x_2} + {x_3} \cr & Subject\,\,to\,\,\,\,\,\,2{x_1} - {x_2} + 3{x_3}\, \le 5 \cr & \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{x_1},{x_2},{x_3} \ge 0 \cr} $$

$$(a)$$$$\,\,\,\,\,\,\,$$ What is the solution to the above problem?

$$(b)$$$$\,\,\,\,\,\,\,$$ Add the constant $${x_2} \le 2$$ to the simplex table of part $$(a)$$ and find the solution.