1
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
A steam plant has the boiler efficiency of $$92\% $$, turbine efficiency (mechanical) of $$94\% $$, generator efficiency of $$92\% $$ and cycle efficiency of $$44\% $$. If $$6\% $$ of the generated power is used to run the auxiliaries, the overall plant efficiency is
A
$$34\% $$
B
$$39\% $$
C
$$45\% $$
D
$$30\% $$
2
GATE ME 1996
Subjective
+5
-0
In a hydroelectric station, water is available at the rate of $$175{m^3}/s$$ under a head of $$18m.$$ The turbines run at a speed of $$150$$ $$rpm$$ with overall efficiency of $$82\% $$. Find the number of turbines required if they have the maximum specific speed of $$460.$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12