1
GATE ME 1996
Subjective
+2
-0
Match List - $${\rm I}$$ with List - $${\rm II}$$ and select the correct answer using the code given below the Lists:

List - $${\rm I}$$
$$A.$$ Grashof number
$$B.$$ Schmid number
$$C.$$ Weber number
$$D.$$ Fourier number

List - $${\rm II}$$
$$1.$$ Mass diffusion
$$2.$$ Transient heat conduction
$$3.$$ Free convection
$$4.$$ Forced convection
$$5.$$ Surface tension
$$6.$$ Radiation

2
GATE ME 1996
MCQ (Single Correct Answer)
+2
-0.6
In an assembly line for assembling toys, five workers are assigned tasks which take times of $$10, 8, 6, 9$$ and $$10$$ minutes respectively. The balance delay for the line is
A
$$43.3\% $$
B
$$14.8\% $$
C
$$14.0\% $$
D
$$16.3\% $$
3
GATE ME 1996
MCQ (Single Correct Answer)
+1
-0.3
If at the optimum in a linear programming problem, a dual variable corresponding to a particular primal constraint is zero, then it means that
A
Right hand side of the primal constraint can be altered without affecting the optimum solution
B
Changing the right hand side of the primal constraint will disturb the optimum solution
C
The objective function is unbounded
D
The problem is degenerate
4
GATE ME 1996
Subjective
+5
-0
A job shop incurs a cost of Rs.$$60$$/- per day for each day a job is in the shop. At the beginning of a month there are five jobs in the shop with the following data: GATE ME 1996 Industrial Engineering - Scheduling Question 4 English

Which schedule will minimize the total cost?
What is the minimum total cost?
Which jobs (if any) fail to meet their due dates?