1
GATE ME 1990
MCQ (Single Correct Answer)
+1
-0.3
Thermal conductivity is lower for
A
wood
B
air
C
water at $${100^ \circ }C$$
D
steam at $$1$$ bar
2
GATE ME 1990
MCQ (Single Correct Answer)
+1
-0.3
In pool boiling the highest $$HTC$$ occurs in
A
Sub-cooled boiling zone
B
Nucleate boiling zone
C
Partial film boiling zone
D
Film boiling zone
3
GATE ME 1990
Subjective
+5
-0
Service workshop has four jobs on hand to be processed. The date and processing time for each of the jobs are given below GATE ME 1990 Industrial Engineering - Scheduling Question 5 English

Considering mean lateness and mean flow time, evaluate the shortest-time rule and least-slack rule and recommend the desirable rule.

4
GATE ME 1990
MCQ (Single Correct Answer)
+2
-0.6
In the construction of networks, dummy activities are introduced in order to :
A
Compute the slack on all events
B
Transfer resources, if necessary, during monitoring
C
Clearly designate a precedence relationship
D
Simplify the crashing plan