1
GATE ME 1990
MCQ (Single Correct Answer)
+2
-0.6
In the construction of networks, dummy activities are introduced in order to :
A
Compute the slack on all events
B
Transfer resources, if necessary, during monitoring
C
Clearly designate a precedence relationship
D
Simplify the crashing plan
2
GATE ME 1990
MCQ (Single Correct Answer)
+1
-0.3
The process of shot peening increases the fatigue life of steel springs mainly because it results in
A
surface hardening
B
increased stiffness of the material
C
structural changes in the material
D
residual compression at the surface
3
GATE ME 1990
MCQ (Single Correct Answer)
+1
-0.3
When $$1.0\% $$ plain carbon steel is slowly cooled from the molten state to $$740C,$$ the resulting structure will contain
A
Pearlite and Cementite
B
Ferrite and Cementite
C
Austinite and Ferrite
D
austenite and Cementite
4
GATE ME 1990
MCQ (Single Correct Answer)
+1
-0.3
In small lot production for machining $$T-$$slots on machine tables, it is expected to use
A
Shaping machine
B
Broaching machine
C
Vertical milling machine
D
Horizontal milling machine
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12