1
GATE EE 2000
Subjective
+5
-0
A synchronous generator, having a reactance of 0.15 p.u., is connected to an infinite bus through two identical parallel transmission lines having reactance of 0.3 p.u. each. In steady state, the generator is delivering 1 p.u. Power to the infinite bus. For a three phase fault at the receiving end of one line, calculate the rotor angle at the end of first time step of 0.05 seconds. Assume the voltage behind transient reactance for the generator as 1.1 p.u. and infinite bus voltage as 1.0 p.u. Also indicate how the accelerating powers will be evaluated for the next time step if the breaker clears the fault.

(i) at the end of an interval
(ii) at the middle of an interval.

2
GATE EE 2000
MCQ (Single Correct Answer)
+2
-0.6
The severity of line-to-ground and three phase faults at the terminals of an unloaded synchronous generator is to be same. If the terminal voltage is
$$1.0$$ p.u. and $${Z_1} = {Z_2} = j0.1\,\,$$ p.u.,
$$\,{Z_0} = j0.05\,\,\,\,\,$$ p.u., for the alternator, then the required inductive reacttance for neutral grounding is
A
$$0.0166$$ p.u.
B
$$0.05$$ p.u.
C
$$0.1$$ p.u.
D
$$0.15$$ p.u.
3
GATE EE 2000
Subjective
+5
-0
For the configuration shown in figure, the breaker connecting a large system to bus $$2$$ is initially open. The system $$3$$-phase fault level at bus $$3$$ under this condition is not known. After closing the system breaker, the $$3$$-phase fault level at bus $$1$$ was found to be $$5.0$$ p.u. What will be the new $$3$$-phase fault level at system bus $$3,$$ after the interconnection? All per unit values are on common base. Prefault load currents are neglected and prefault voltages are assumed to be $$1.0$$ p.u. at all buses. GATE EE 2000 Power System Analysis - Symmetrical Components and Symmetrical and Unsymmetrical Faults Question 7 English
4
GATE EE 2000
MCQ (Single Correct Answer)
+1
-0.3
In a 3-step distance protection, the reach of the three zones of the relay at the beginning of the first line typically extends upto
A
100% of the first line, 50% of the second line and 20% of the third line.
B
80% of the first line, 50% of the second line and 20% of the third line.
C
80% of the first line, 20% of the second line and 10% of the third line.
D
50% of first line, 50% of second line and 20% of the third line.
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12