1
GATE ME 1993
Subjective
+5
-0
For a small project with five jobs, the following data is given GATE ME 1993 Industrial Engineering - Pert and Cpm Question 7 English
(i) Draw the project network in activity on arc mode
(ii) Under $$PERT$$ assumptions, determine the distribution of project duration.
2
GATE ME 1993
MCQ (Single Correct Answer)
+1
-0.3
The outside diameter of a hollow shaft is twice its inside diameter. The ratio of its torque carrying capacity to that of a solid shaft of the same material and the same outside diameter is
A
$$15/16$$
B
$$3/4$$
C
$$1/2$$
D
$$1/16$$
3
GATE ME 1993
MCQ (Single Correct Answer)
+1
-0.3
The yield strength of a steel shaft is twice its endurance limit. Which of the following torque fluctuations represent the most critical situation according to Soderberg criterion?
A
$$-T$$ to $$+T$$
B
$$-T/2$$ to $$+T$$
C
$$0$$ to $$+T$$
D
$$+T/2$$ to $$+T$$
4
GATE ME 1993
MCQ (More than One Correct Answer)
+1
-0
Centrifugally casted products have
A
Large grain structure with high porosity
B
Fine grain structure with high density
C
Fine grain structure with low density
D
Segregation of slug towards the outer skin of the casting
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12