Consider the following data for a project of 300 days duration.

Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190

The ‘schedule variance’ for the project is

A

(−)Rs. 50

B

(−)50 days

C

(+)Rs. 50

D

(+)50 days

2
GATE CE 2024 Set 2
MCQ (Single Correct Answer)
+2
-0.833

A critical activity in a project is estimated to take 15 days to complete at a cost of Rs. 30,000. The activity can be expedited to complete in 12 days by spending a total amount of Rs. 54,000. Consider the statements P and Q.

P: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 8,500 per day.

Q: It is economically advisable to complete the activity early by crashing, if the indirect cost of the project is Rs. 10,000 per day.

Which one of the following options is CORRECT?

A

Both P and Q are TRUE

B

P is TRUE and Q is FALSE

C

Both P and Q are FALSE

D

P is FALSE and Q is TRUE

3
GATE CE 2024 Set 2
MCQ (More than One Correct Answer)
+2
-0.833

In the context of pavement material characterization, the CORRECT statement(s) is/are

A

The load penetration curve of CBR test may need origin correction due to the non-vertical penetrating plunger of the loading machine.

B

The toughness and hardness of road aggregates are determined by Los Angeles abrasion test and aggregate impact test, respectively.

C

Grading of normal (unmodified) bitumen binders is done based on viscosity test results.

D

In compacted bituminous mix, Voids in the Mineral Aggregate (VMA) is equal to the sum of total volume of air voids (Va) and total volume of bitumen (Vb).

4
GATE CE 2024 Set 2
Numerical
+2
-0.833

The table shows the activities and their durations and dependencies in a project.

ActivityDuration (Days)Depends on
A8-
B4A
C4B
D4C, L
F4A
G4F
H6G, L
K10A
L6F, K

The total duration (in days) of the project is __________ (in integer).

Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12