1
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+2
-0.6
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity $$4$$-$$6$$ and the project duration, respectively, are GATE ME 2014 Set 3 Industrial Engineering - Pert and Cpm Question 13 English
A
$$2, 13$$
B
$$0, 13$$
C
$$-2, 13$$
D
$$2, 12$$
2
GATE ME 2014 Set 3
Numerical
+1
-0
The actual sales of a product in different months of a particular year are given below: GATE ME 2014 Set 3 Industrial Engineering - Forecasting Question 12 English

The forecast of the sales, using the 4-month moving average method, for the month of February is ____________.

Your input ____
3
GATE ME 2014 Set 3
Numerical
+2
-0
Consider an objective function $$Z\left( {{x_1},{x_2}} \right) = 3{x_1} + 9{x_2}$$ and the constraints
$$\eqalign{ & {x_1} + {x_2} \le 8, \cr & {x_1} + 2{x_2} \le 4, \cr & {x_1} \ge 0,{x_2} \ge 0, \cr} $$

The maximum value of the objective function is ________________.

Your input ____
4
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following is NOT correct?
A
Intermediate principal stress is ignored when applying the maximum principal stress theory
B
The maximum shear stress theory gives the most accurate results amongst all the failure theories
C
As per the maximum strain energy theory, failure occurs when the strain energy per unit volume exceeds a critical value
D
As per the maximum distortion energy theory, failure occurs when the distortion energy per unit volume exceeds a critical value
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12