1
GATE ME 2014 Set 3
Numerical
+2
-0
A double-pipe counter-flow heat exchanger transfers heat between two water streams. Tube side water at $$19$$ liter/s is heated from $${10^ \circ }C$$ to $${38^ \circ }C$$. Shell side water at $$25$$ liter/s is entering at $${46^ \circ }C$$. Assume constant properties of water; density is $$1000\,kg/{m^3}$$ and specific heat is $$4186$$ $$J/kg.K.$$ The $$LMTD$$ (in $${}^ \circ C$$) is ____________.
Your input ____
2
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+2
-0.6
A manufacturer can produce $$12000$$ bearings per day. The manufacturer received an order of $$8000$$ bearings per day from a customer. The cost of holding a bearing in stock is Rs. $$0.20$$ per month. Setup cost per production run in Rs.$$500.$$ Assuming $$300$$ working days in a year, the frequency of production run should be
A
$$4.5$$ days
B
$$4.5$$ months
C
$$6.8$$ days
D
$$6.8$$ months
3
GATE ME 2014 Set 3
MCQ (Single Correct Answer)
+2
-0.6
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity $$4$$-$$6$$ and the project duration, respectively, are GATE ME 2014 Set 3 Industrial Engineering - Pert and Cpm Question 13 English
A
$$2, 13$$
B
$$0, 13$$
C
$$-2, 13$$
D
$$2, 12$$
4
GATE ME 2014 Set 3
Numerical
+1
-0
The actual sales of a product in different months of a particular year are given below: GATE ME 2014 Set 3 Industrial Engineering - Forecasting Question 12 English

The forecast of the sales, using the 4-month moving average method, for the month of February is ____________.

Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering