In a power-system, the $$3$$-phase fault MVA is always higher than the single-line-ground fault MVA at a bus (State True or False)
A
TRUE
B
FALSE
2
GATE EE 1994
MCQ (Single Correct Answer)
+1
-0.3
HVDC transmission is preferred to EHV __ AC because
A
HVDC terminal equipment are inexpensive
B
VAR compensation is not required in HVDC systems
C
System stability can be improved.
D
Harmonics __ problem is avoided
3
GATE EE 1994
Subjective
+1
-0
If $$f(t)$$ is the step-response of a linear time-invariant system, then its impulse response is given by ___________
4
GATE EE 1994
Fill in the Blanks
+1
-0
The value of the integral $$\int_{-5}^{+6}e^{-2t}\delta\left(t-1\right)dt$$ is equal to ________.
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12