1
GATE CSE 2015 Set 3
MCQ (Single Correct Answer)
+2
-0.6
For the processes listed in the following table, which of the following scheduling schemes will give the lowest average turnaround time?

Process Arrival Time Processing Time
A 0 3
B 1 6
D 4 4
E 6 2

A
First Come First Serve
B
Non-preemptive Shortest Job First
C
Shortest Remaining Time
D
Round Robin with Quantum value two
2
GATE CSE 2015 Set 3
MCQ (Single Correct Answer)
+1
-0.3
The maximum number of processes that can be in $$Ready$$ state for a computer system with $$n$$ $$CPUs$$ is
A
$$n$$
B
$${n^2}$$
C
$${2^n}$$
D
Independent of $$n$$
3
GATE CSE 2015 Set 3
MCQ (Single Correct Answer)
+1
-0.3
Consider the following C program segment.
#include < stdio.h >
int main()
{
    char s1[7] = "1234", *p;
    p = s1 + 2;
   *p = ā€˜0ā€™;
    printf("%s", s1);
}
What will be printed by the program?
A
12
B
120400
C
1204
D
1034
4
GATE CSE 2015 Set 3
Numerical
+1
-0
Consider a software program that is artificially seeded with $$100$$ faults. While testing this program, $$159$$ faults are detected, out of which $$75$$ faults are from those artificially seeded faults. Assuming that both real and seeded faults are of same nature and have same distribution, the estimated number of undetected real faults is ____________.
Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12