1
GATE CE 2024 Set 1
Numerical
+2
-0

The ordinates of a 1-hour unit hydrograph (UH) are given below.

Time (hours) 0 1 2 3 4 5
Ordinates of 1-hour UH (m3/s) 0 13 50 80 95 85
Time (hours) 6 7 8 9 10 11
Ordinates of 1-hour UH (m3/s) 55 35 15 10 3 0

These ordinates are used to derive a 3-hour UH. The peak discharge (in m3/s) for the derived 3-hour UH is ___________ (rounded off to the nearest integer).

Your input ____
2
GATE CE 2024 Set 1
Numerical
+2
-0

A spillway has unit discharge of 7.5 m3/s/m. The flow depth at the downstream horizontal apron is 0.5 m. The tail water depth (in meters) required to form a hydraulic jump is ___________ (rounded off to 2 decimal places).

Your input ____
3
GATE CE 2024 Set 1
MCQ (Single Correct Answer)
+1
-0.33

The following figure shows the arrangement of formwork for casting a cantilever RC beam.

GATE CE 2024 Set 1 Reinforced Cement Concrete - Workmenship and Fundamentals Question 2 English

The correct sequence of removing the Shores/Props is:

A

S1 → S2 → S3 → S4 → S5

B

S5 → S4 → S3 → S2 → S1

C

S3 → S2 → S4 → S1 → S5

D

S3 → S4 → S2 → S5 → S1

4
GATE CE 2024 Set 1
MCQ (More than One Correct Answer)
+1
-0

Consider a balanced doubly-reinforced concrete section. If the material and other sectional properties remain unchanged, for which of the following cases will the section becomes under-reinforced?

A

Area of tension reinforcement is increased.

B

Area of compression reinforcement is increased.

C

Area of tension reinforcement is decreased.

D

Area of compression reinforcement is decreased.

EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12