1
GATE CE 2012
MCQ (Single Correct Answer)
+2
-0.6
Wheat crop requires 55 cm of water during 120 days of base period. The total rainfall during this period is 100 mm. Assume the irrigation efficiency to be 60%. The area (in ha) of the land which can be irrigated with a canal flow of 0.01 $$m^3/s$$ is
2
GATE CE 2012
MCQ (Single Correct Answer)
+2
-0.6
A concrete beam prestressed with a parabolic tendon is shown in the sketch. The eccentricity of the tendon is measured from the centroid of the cross-section. The applied prestressing force at service is $$1620$$ $$kN.$$ The uniformly distributed load of $$45$$ $$kN/m$$ includes the self-weight. The stress (in $$N/m{m^2}$$) in the bottom fibre at mid-span is
3
GATE CE 2012
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following is categorized as a long-term loss of prestress in a prestressed concrete member?
4
GATE CE 2012
MCQ (Single Correct Answer)
+2
-0.6
The cross-section at mid-span of a beam at the edge of a slab is shown in the sketch. $$A$$ portion of the slab is considered as the effective flange width for the beam. The grades of concrete and reinforcing steel are $$M25$$ and $$Fe415,$$ respectively. The total area of reinforcing bars $$\left( {{A_{st}}} \right),$$ is $$\,4000\,\,m{m^2}.$$ At the ultimate limit state, $${x_u}$$ denotes the depth of the neutral axis from the top fibre. Treat the section as under-reinforced and flanged $$\left( {{x_u} > 100\,\,mm} \right).$$
The value of $${{x_u}}$$ (in $$mm$$) computed per the Limit State Method of $$IS$$ $$456:2000$$ is
Paper analysis
Total Questions
Engineering Mathematics
7
Environmental Engineering
1
Fluid Mechanics and Hydraulic Machines
1
Hydrology
1
Irrigation
1
Reinforced Cement Concrete
5
Steel Structures
2
Strength of Materials Or Solid Mechanics
6
Structural Analysis
1
More papers of GATE CE
GATE CE 2024 Set 2
GATE CE 2024 Set 1
GATE CE 2023 Set 2
GATE CE 2023 Set 1
GATE CE 2022 Set 2
GATE CE 2022 Set 1
GATE CE 2018 Set 1
GATE CE 2018 Set 2
GATE CE 2017 Set 1
GATE CE 2017 Set 2
GATE CE 2016 Set 2
GATE CE 2016 Set 1
GATE CE 2015 Set 2
GATE CE 2015 Set 1
GATE CE 2014 Set 1
GATE CE 2014 Set 2
GATE CE 2013
GATE CE 2012
GATE CE 2011
GATE CE 2010
GATE CE 2009
GATE CE 2008
GATE CE 2007
GATE CE 2006
GATE CE 2005
GATE CE 2004
GATE CE 2003
GATE CE 2002
GATE CE 2001
GATE CE 2000
GATE CE 1999
GATE CE 1998
GATE CE 1997
GATE CE 1996
GATE CE 1995
GATE CE 1994
GATE CE 1993
GATE CE 1992
GATE CE 1991
GATE CE 1990
GATE CE 1989
GATE CE 1988
GATE CE 1987
GATE CE
Papers
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
1994
1993
1992
1991
1990
1989
1988
1987