1
GATE CE 2002
MCQ (Single Correct Answer)
+1
-0.3
Eigen values of the following matrix are $$\left[ {\matrix{ { - 1} & 4 \cr 4 & { - 1} \cr } } \right]$$
A
$$3, -5$$
B
$$-3, 5$$
C
$$-3, -5$$
D
$$3,5$$
2
GATE CE 2002
MCQ (Single Correct Answer)
+1
-0.3
In natural water, hardness is mainly caused by
A
$$Ca^{++}$$ and $$Mn^{++}$$
B
$$Ca^{++}$$ and $$Fe^{++}$$
C
$$Na^{+}$$ and $$K^{+}$$
D
$$Ca^{++}$$ and $$Mg^{++}$$
3
GATE CE 2002
MCQ (Single Correct Answer)
+2
-0.6
During a 6-hour storm the rainfall intensity was 0.8 cm/hr on a catchment of area 8.6 km2. The measured runoff volume during this period was 2,56,000 m3. The total rainfall was lost due to infiltration, evaporation and transpiration in cm/hr is
A
0.80
B
0.304
C
0.496
D
Sufficient information not available
4
GATE CE 2002
Subjective
+5
-0
A $$10m$$ long prestressing bed is used to cast $$4$$ (pretensioned) prestressed concrete beams of $$2.3$$ $$m$$ each. A schematic representation of the bed is given in the following figure. The continuous prestressing reinforced is pulled at the end $$'Y'$$ of the bed through a distance of $$20$$ $$mm$$ to introduce the required prestress, before the concrete is cast. After the concrete has hardened, the prestressing reinforcement is cut at points $$A,B,C,D$$ and $$E.$$ Assume that the prestress is introduced without eccentricity, what is the loss in prestress on account of elastic deformation of concrete. Assume $${E_s} = 200000\,\,N/m{m^2},$$ reinforcement is $$500\,\,m{m^2},$$ size of beams $$ = 200\,\,mm\,\left( b \right) \times 400\,\,mm\,\left( h \right).$$ GATE CE 2002 Reinforced Cement Concrete - Prestressed Concrete Question 3 English
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12