The figure shows a network diagram for a construction project. The activities $\mathrm{A}, \mathrm{B}, \mathrm{C}$, D, E, and F are represented by arrows and their durations are in the figure.
The total float available for the activity E in day(s) is equal to _________ (round off to the nearest integer).