1
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Let the characteristic strength be defined as that value, below which not more than 50% of the
results are expected to fall. Assuming a standard deviation of 4 MPa, the target mean strength
(in MPa) to be considered in the mix design of a M25 concrete would be
2
GATE CE 2017 Set 2
Numerical
+2
-0
Two plates of $$8$$ $$mm$$ thickness each are connected by a fillet weld of $$6$$ $$mm$$ thickness as shown in the figure.
The permissible stresses in the plate and the weld are $$150$$ $$MPa$$ and $$110$$ $$MP,$$ respectively. Assuming the length of the weld shown in the figure to be the effective length, the permissible load $$P$$ (in $$kN$$) is _____________.
Your input ____
3
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+2
-0.6
Two prismatic beams having the same flexural rigidity of $$1000\,kN$$-$${m^2}$$ are shown in the figures.
If the mid-span deflections of these beams are denoted by $${\delta _1}$$ and $${\delta _2}$$ (as indicated in the figures), the correct option is
4
GATE CE 2017 Set 2
Numerical
+2
-0
A hollow circular shaft has an outer diameter of $$100$$ $$mm$$ and inner diameter of $$50mm.$$ If the allowable shear stress is $$125$$ $$MPa$$, the maximum torque (in $$kN$$-$$m$$) that the shaft can resist is ___________
Your input ____
Paper analysis
Total Questions
Construction Material and Management
3
Engineering Mathematics
7
Environmental Engineering
1
Fluid Mechanics and Hydraulic Machines
1
Hydrology
1
Irrigation
1
Reinforced Cement Concrete
2
Steel Structures
1
Strength of Materials Or Solid Mechanics
4
Structural Analysis
2
Transportation Engineering
1
More papers of GATE CE
GATE CE 2024 Set 2
GATE CE 2024 Set 1
GATE CE 2023 Set 2
GATE CE 2023 Set 1
GATE CE 2022 Set 2
GATE CE 2022 Set 1
GATE CE 2018 Set 1
GATE CE 2018 Set 2
GATE CE 2017 Set 1
GATE CE 2017 Set 2
GATE CE 2016 Set 2
GATE CE 2016 Set 1
GATE CE 2015 Set 2
GATE CE 2015 Set 1
GATE CE 2014 Set 1
GATE CE 2014 Set 2
GATE CE 2013
GATE CE 2012
GATE CE 2011
GATE CE 2010
GATE CE 2009
GATE CE 2008
GATE CE 2007
GATE CE 2006
GATE CE 2005
GATE CE 2004
GATE CE 2003
GATE CE 2002
GATE CE 2001
GATE CE 2000
GATE CE 1999
GATE CE 1998
GATE CE 1997
GATE CE 1996
GATE CE 1995
GATE CE 1994
GATE CE 1993
GATE CE 1992
GATE CE 1991
GATE CE 1990
GATE CE 1989
GATE CE 1988
GATE CE 1987
GATE CE
Papers
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
1994
1993
1992
1991
1990
1989
1988
1987