1
GATE CE 2017 Set 2
Numerical
+1
-0
For a construction project. The mean and standard deviation of the completion time are 200
days and 6.1 days, respectively. Assume normal distribution and use the value of standard
normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days)
for the completion of the project would be __________.
Your input ____
2
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+2
-0.6
Consider the following statements:
P. Walls of one brick thick are measured in square meters.
Q. Walls of one brick thick are measured in cubic meters.
R. No deduction in the brickwork quantity is made for openings in walls up to 0.1 $$m^2$$ area.
S. For the measurement of excavation from the borrow pit in a fairly uniform ground, dead men are left at suitable intervals.
For the above statements, the correct option is
P. Walls of one brick thick are measured in square meters.
Q. Walls of one brick thick are measured in cubic meters.
R. No deduction in the brickwork quantity is made for openings in walls up to 0.1 $$m^2$$ area.
S. For the measurement of excavation from the borrow pit in a fairly uniform ground, dead men are left at suitable intervals.
For the above statements, the correct option is
3
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Given that the scope of the construction work is well-defined with all its drawings,
specifications, quantities and estimates, which one of the following types of contract would be
most preferred?
4
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Let $$\,\,W = f\left( {x,y} \right),\,\,$$ where $$x$$ and $$y$$ are functions of $$t.$$ Then, according to the chain rule, $${{dw} \over {dt}}$$ is equal to
Paper analysis
Total Questions
Construction Material and Management
3
Engineering Mathematics
7
Environmental Engineering
1
Fluid Mechanics and Hydraulic Machines
1
Hydrology
1
Irrigation
1
Reinforced Cement Concrete
2
Steel Structures
1
Strength of Materials Or Solid Mechanics
4
Structural Analysis
2
Transportation Engineering
1
More papers of GATE CE
GATE CE 2024 Set 2
GATE CE 2024 Set 1
GATE CE 2023 Set 2
GATE CE 2023 Set 1
GATE CE 2022 Set 2
GATE CE 2022 Set 1
GATE CE 2018 Set 1
GATE CE 2018 Set 2
GATE CE 2017 Set 1
GATE CE 2017 Set 2
GATE CE 2016 Set 2
GATE CE 2016 Set 1
GATE CE 2015 Set 2
GATE CE 2015 Set 1
GATE CE 2014 Set 1
GATE CE 2014 Set 2
GATE CE 2013
GATE CE 2012
GATE CE 2011
GATE CE 2010
GATE CE 2009
GATE CE 2008
GATE CE 2007
GATE CE 2006
GATE CE 2005
GATE CE 2004
GATE CE 2003
GATE CE 2002
GATE CE 2001
GATE CE 2000
GATE CE 1999
GATE CE 1998
GATE CE 1997
GATE CE 1996
GATE CE 1995
GATE CE 1994
GATE CE 1993
GATE CE 1992
GATE CE 1991
GATE CE 1990
GATE CE 1989
GATE CE 1988
GATE CE 1987
GATE CE
Papers
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
1994
1993
1992
1991
1990
1989
1988
1987