GATE CE 2017 Set 2
Numerical
+1
-0
For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________.
Your input ____
2
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+2
-0.6
If $$A = \left[ {\matrix{ 1 & 5 \cr 6 & 2 \cr } } \right]\,\,and\,\,B = \left[ {\matrix{ 3 & 7 \cr 8 & 4 \cr } } \right]A{B^T}$$ is equal to
A
$$\left[ {\matrix{ {38} & {28} \cr {32} & {56} \cr } } \right]$$
B
$$\left[ {\matrix{ 3 & {40} \cr {42} & 8 \cr } } \right]$$
C
$$\left[ {\matrix{ {43} & {27} \cr {34} & {50} \cr } } \right]$$
D
$$\left[ {\matrix{ {38} & {32} \cr {28} & {56} \cr } } \right]$$
3
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Consider the following simultaneous equations (with $${c_1}$$ and $${c_2}$$ being constants): $$$3{x_1} + 2{x_2} = {c_1}$$$ $$$4{x_1} + {x_2} = {c_2}$$$

The characteristic equation for these simultaneous equation is

A
$${\lambda ^2} - 4\lambda - 5 = 0$$
B
$${\lambda ^2} 4\lambda + 5 = 0$$
C
$${\lambda ^2} + 4\lambda - 5 = 0$$
D
$${\lambda ^2} + 4\lambda + 5 = 0$$
4
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Let $$\,\,W = f\left( {x,y} \right),\,\,$$ where $$x$$ and $$y$$ are functions of $$t.$$ Then, according to the chain rule, $${{dw} \over {dt}}$$ is equal to
A
$${{dw} \over {dx}}{{dx} \over {dt}} + {{dw} \over {dy}}{{dt} \over {dt}}$$
B
$${{\partial w} \over {\partial x}}{{\partial x} \over {\partial t}} + {{\partial w} \over {\partial y}}{{\partial y} \over {\partial t}}$$
C
$${{\partial w} \over {\partial x}}{{dx} \over {dt}} + {{\partial w} \over {\partial y}}{{dy} \over {dt}}$$
D
$${{dw} \over {dx}}{{\partial x} \over {\partial t}} + {{dw} \over {dy}}{{\partial y} \over {\partial t}}$$