GATE CE 2015 Set 1
MCQ (Single Correct Answer)
+1
-0.3
Workability of concrete can be measured using slump, compaction factor and Vee bee time. Consider the following statements for workability of concrete:

(i) As the slump increases, the Vebe time increases

(ii) As the slum increases, the compaction factor increases

Which of the following is TRUE?
A
Both (i) and (ii) are True
B
Both (i) and (ii) are False
C
(i) is True and (ii) is False
D
(i) is False and (ii) is True
2
GATE CE 2015 Set 1
Numerical
+2
-0
The composition of an air-entrained concrete is given below:

Water : 184 kg /m3

Ordinary Portland Cement(OPC) : 368 kg /m3

Sand : 606 kg /m3

Coarse aggregate : 1155 kg /m3

Assume the specific gravity of OPC, sand and coarse aggregate to be 3.14, 2.67 and 2.74, respectively. The air content is_________ liters/m3
Your input ____
3
GATE CE 2015 Set 1
MCQ (Single Correct Answer)
+1
-0.3
Consider the following statements for air-entrained concrete:

(i) Air-entrainment reduces the water demand for a given level of workability

(ii) Use of air-entrained concrete is required in environments where cyclic freezing and thawing is expected.

Which of the following is TRUE?
A
Both (i) and (ii) are True
B
Both (i) and (ii) are False
C
(i) is True and (ii) is False
D
(i) is False and (ii) is True
4
GATE CE 2015 Set 1
Numerical
+2
-0
A bracket plate connected to a column flange transmits a load of $$100$$ $$kN$$ as shown in the following figure. The maximum force for which the bolts should be designed is _______ $$kN$$ GATE CE 2015 Set 1 Steel Structures - Eccentric Connections Question 4 English
Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12