1
GATE CE 1997
MCQ (Single Correct Answer)
+1
-0.3
Lysimeter and Tensiometer are used to measure respectively, one of the following groups of quantities:
A
Capillary potential and permeability
B
Evapotranspiration and capillary potential
C
Velocity in channels and vapour pressure
D
Velocity in pipes and pressure head
2
GATE CE 1997
MCQ (Single Correct Answer)
+1
-0.3
Hyetograph is a graph representing
A
rainfall volume with time
B
rainfall intensity with time
C
rainfall intensity with duration
D
rainfall intensity over an area
3
GATE CE 1997
MCQ (Single Correct Answer)
+2
-0.6
A prestressed concrete rectangular beam of size $$300\,\,mm \times 900\,\,mm$$ is prestressed with an intial prestressing force of $$700$$ $$kN$$ at an eccentricity of $$350$$ $$mm$$ at midspan. Stress at top due to prestress alone, in $$N/m{m^2}$$ is
A
$$-3.46$$ (tension)
B
$$2.59$$ (compression)
C
zero
D
$$8.64$$ (compression)
4
GATE CE 1997
Subjective
+2
-0
Design a square $$R.C$$ column to resist an axial load of $$400$$ $$kN$$ due to dead load and $$240$$ $$kN$$ due to live load at service stage. Design the section as a short axially loaded column. Use $$M25$$ concrete and steel of grade $$415$$ $$N/m{m^2}.$$ Give a near sketch of the cross section.
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12