1
GATE CE 2016 Set 2
Numerical
+1
-0
The hardness of a ground water sample was found to be 420 mg/L as $$CaCO_3$$. A softener
containing ion exchange resins was installed to reduce the total hardness to 75 mg/L as
$$CaCO_3$$ before supplying to 4 households. Each household gets treated water at a rate of 540
L/day. If the efficiency of the softener is 100%, the bypass flow rate (expressed in L/day) is
.
Your input ____
2
GATE CE 2016 Set 2
Numerical
+2
-0
A launched (varying depth) reinforced concrete beam is simply supported at both ends, as shown in the figure. The beam is subjected to a uniformly distributed factored load of intensity $$10$$ $$kN/m.$$ The design shear force (expressed in $$kN$$) at the section $$X$$-$$X$$ of the beam is ____________
Your input ____
3
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
As per $$IS$$ $$456$$ - $$2000$$ for the design of reinforced concrete beam, the maximum allowable shear stress $$\left( {{\tau _{c\,\,\max }}} \right)$$ depends on the
4
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
Two bolted plates under tension with alternative arrangement of bolt holes are shown in figures $$1$$ and $$2.$$ The hole diameter, pitch, and gauge length are $$d, p$$ and $$g$$ respectively.
Which one of the following conditions must be ensured to have higher net tensile capacity of configuration shown in figure $$2$$ than that shown in figure $$1$$?
Paper analysis
Total Questions
Construction Material and Management
3
Engineering Mathematics
5
Engineering Mechanics
1
Environmental Engineering
2
Reinforced Cement Concrete
2
Steel Structures
1
Strength of Materials Or Solid Mechanics
3
Structural Analysis
4
Transportation Engineering
1
More papers of GATE CE
GATE CE 2024 Set 2
GATE CE 2024 Set 1
GATE CE 2023 Set 2
GATE CE 2023 Set 1
GATE CE 2022 Set 2
GATE CE 2022 Set 1
GATE CE 2018 Set 1
GATE CE 2018 Set 2
GATE CE 2017 Set 1
GATE CE 2017 Set 2
GATE CE 2016 Set 2
GATE CE 2016 Set 1
GATE CE 2015 Set 2
GATE CE 2015 Set 1
GATE CE 2014 Set 1
GATE CE 2014 Set 2
GATE CE 2013
GATE CE 2012
GATE CE 2011
GATE CE 2010
GATE CE 2009
GATE CE 2008
GATE CE 2007
GATE CE 2006
GATE CE 2005
GATE CE 2004
GATE CE 2003
GATE CE 2002
GATE CE 2001
GATE CE 2000
GATE CE 1999
GATE CE 1998
GATE CE 1997
GATE CE 1996
GATE CE 1995
GATE CE 1994
GATE CE 1993
GATE CE 1992
GATE CE 1991
GATE CE 1990
GATE CE 1989
GATE CE 1988
GATE CE 1987
GATE CE
Papers
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
1994
1993
1992
1991
1990
1989
1988
1987