1
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. GATE CE 2016 Set 2 Construction Material and Management - Critical Path Method Question 8 English The critical duration for this construction project is
A
13 days
B
14 days
C
15 days
D
16 days
2
GATE CE 2016 Set 2
Numerical
+1
-0
The spot speeds (expressed in km/hr) observed at a road section are $$66, 62, 45, 79, 32, 51, 56, 60, 53$$ and $$49.$$ The median speed (expressed in km/hr) is __________.
Your input ____
3
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
The quadratic approximation of $$f\left( x \right) = {x^3} - 3{x^2} - 5\,\,$$ at the point $$x=0$$ is
A
$$3{x^2} - 6x - 5$$
B
$$ - 3{x^2} - 5$$
C
$$ - 3{x^2} + 6x - 5$$
D
$$3{x^2} - 5$$
4
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+2
-0.6
If $$f(x)$$ and $$g(x)$$ are two probability density functions, $$$f\left( x \right) = \left\{ {\matrix{ {{x \over a} + 1} & : & { - a \le x < 0} \cr { - {x \over a} + 1} & : & {0 \le x \le a} \cr 0 & : & {otherwise} \cr } } \right.$$$ $$$g\left( x \right) = \left\{ {\matrix{ { - {x \over a}} & : & { - a \le x < 0} \cr {{x \over a}} & : & {0 \le x \le a} \cr 0 & : & {otherwise} \cr } } \right.$$$

Which of the following statements is true?

A
Mean of $$f(x)$$ and $$g(x)$$ are same; Variance of $$f(x)$$ and $$g(x)$$ are same .
B
Mean of $$f(x)$$ and $$g(x)$$ are same ; Variance of $$f(x)$$ and $$g(x)$$ are different.
C
Mean of $$f(x)$$ and $$g(x)$$ are different ; Variance of $$f(x)$$ and $$g(x)$$ are same .
D
Mean of $$f(x)$$ and $$g(x)$$ are different; Variance of $$f(x)$$ and $$g(x)$$ are different.