The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P. GATE CE 2016 Set 1 Construction Material and Management - Program Evolution Review Technique Question 4 English The expected completion time (in days) of the project is _______.
Your input ____
2
GATE CE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
The compound which is largely responsible for initial setting and early strength gain of Ordinary Portland Cement is
A
$$C_3A$$
B
$$C_3S$$
C
$$C_2S$$
D
$$C_4AF$$
3
GATE CE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
Bull's trench kiln is used in the manufacturing of
A
Lime
B
Cement
C
Bricks
D
none of these
4
GATE CE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
The type of partial differential equation $${{{\partial ^2}p} \over {\partial {x^2}}} + {{{\partial ^2}p} \over {\partial {y^2}}} + 3{{{\partial ^2}p} \over {\partial x\partial y}} + 2{{\partial p} \over {\partial x}} - {{\partial p} \over {\partial y}} = 0$$ is
A
elliptic
B
parabolic
C
hyperbolic
D
none of these
EXAM MAP