1
GATE CE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
The compound which is largely responsible for initial setting and early strength gain of Ordinary Portland Cement is
A
$$C_3A$$
B
$$C_3S$$
C
$$C_2S$$
D
$$C_4AF$$
2
GATE CE 2016 Set 1
Numerical
+2
-0
The Optimistic Time (O), most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P. GATE CE 2016 Set 1 Construction Material and Management - Program Evolution Review Technique Question 4 English The expected completion time (in days) of the project is _______.
Your input ____
3
GATE CE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
Bull's trench kiln is used in the manufacturing of
A
Lime
B
Cement
C
Bricks
D
none of these
4
GATE CE 2016 Set 1
Numerical
+2
-0
Newton-Raphson method is to be used to find root of equation $$\,3x - {e^x} + \sin \,x = 0.\,\,$$ If the initial trial value for the root is taken as $$0.333,$$ the next approximation for the root would be _________ (note: answer up to three decimal)
Your input ____