1
GATE CE 2015 Set 2
MCQ (Single Correct Answer)
+1
-0.3
If the water content of a fully saturated soil mass is 100%, the void ratio of the sample is
2
GATE CE 2015 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The average surface area of a reservoir in the month of June is 20 km2. In the same month, the average rate of inflow is 10 m3/s, outflow rate is 15 m3/s, monthly rainfall is 10 cm, monthly seepage loss is 1.8 cm and the storage change is 16 million m3. The evaporation (in cm) in that month is
3
GATE CE 2015 Set 2
MCQ (Single Correct Answer)
+2
-0.6
In a pre-stressed concrete beam section shown in the figure, the net loss is $$10\% $$ and the final prestressing force applied at $$X$$ is $$750$$ $$kN.$$ The initial fiber stresses (in $$N/m{m^2}$$ ) at the top and bottom of the beam were:
4
GATE CE 2015 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A column of size $$450\,mm \times 600\,mm$$ has unsupported length of $$3.0$$ $$m$$ and is braced against side sway in both directions. According to $$IS$$ $$456: 2000,$$ the minimum eccentricities (in $$mm$$) with respect to major and minor principal axes are:
Paper analysis
Total Questions
Engineering Mathematics
9
Environmental Engineering
1
Fluid Mechanics and Hydraulic Machines
1
Geotechnical Engineering
2
Hydrology
1
Reinforced Cement Concrete
3
Steel Structures
2
Strength of Materials Or Solid Mechanics
4
Structural Analysis
4
Transportation Engineering
1
More papers of GATE CE
GATE CE 2024 Set 2
GATE CE 2024 Set 1
GATE CE 2023 Set 2
GATE CE 2023 Set 1
GATE CE 2022 Set 2
GATE CE 2022 Set 1
GATE CE 2018 Set 1
GATE CE 2018 Set 2
GATE CE 2017 Set 2
GATE CE 2017 Set 1
GATE CE 2016 Set 2
GATE CE 2016 Set 1
GATE CE 2015 Set 1
GATE CE 2015 Set 2
GATE CE 2014 Set 1
GATE CE 2014 Set 2
GATE CE 2013
GATE CE 2012
GATE CE 2011
GATE CE 2010
GATE CE 2009
GATE CE 2008
GATE CE 2007
GATE CE 2006
GATE CE 2005
GATE CE 2004
GATE CE 2003
GATE CE 2002
GATE CE 2001
GATE CE 2000
GATE CE 1999
GATE CE 1998
GATE CE 1997
GATE CE 1996
GATE CE 1995
GATE CE 1994
GATE CE 1993
GATE CE 1992
GATE CE 1991
GATE CE 1990
GATE CE 1989
GATE CE 1988
GATE CE 1987
GATE CE
Papers
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
2000
1999
1998
1997
1996
1995
1994
1993
1992
1991
1990
1989
1988
1987