The creep strains are
A
caused due to dead loads only
B
caused due to live loads only
C
caused due to cyclic loads only
D
independent of loads
2
GATE CE 2013
Numerical
+1
-0
As per $$IS$$ $$456:2000$$ for $$M20$$ grade concrete and plain barsin tension the design bond stress $${\tau _{bd}} = 1.2\,\,MPa.$$ Further, $$IS$$ $$456:2000$$ permits this design bond stress value to be increased by $$60\% $$ for $$HYSD$$ bars. The stress in the $$HYSD$$ reinforcing steel bars in tension $${\sigma _s} = 360\,MPa.$$ Find the required development length, $${L_d},$$ for $$HYSD$$ bars in terms of the bar diameter, $$\phi $$ ______________.
Your input ____
3
GATE CE 2013
MCQ (Single Correct Answer)
+1
-0.3
Maximum possible value of compaction factor for fresh (green) concrete is
A
0.5
B
1.0
C
1.5
D
2.0
4
GATE CE 2013
Numerical
+1
-0
A symmetric $${\rm I}$$-section (with width of each flange $$=50$$ $$mm$$, thickness of each flange $$=10$$ $$mm,$$ depth of web $$= 100$$ $$mm,$$ and thickness of web $$=10$$ $$mm$$ ݉݉) of steel is subjected to a shear force of $$100$$ $$kN.$$ Find the magnitude of the shear stress (in ܰ$$N/m{m^2}$$) in the web at its junction with the top flange. ___________