1
GATE CE 2000
MCQ (Single Correct Answer)
+1
-0.3
A soil sample has a void ratio of 0.5 and its porosity will be closed to
A
50%
B
66%
C
100%
D
33%
2
GATE CE 2000
MCQ (Single Correct Answer)
+1
-0.3
A borrow pit soil has a dry density of 17 kN/m3. How many cubic meters of this soils will be required to construct an embankment of 100 m3 volume with a dry density of 16 kN/m3.
A
94 m3
B
106 m3
C
100 m3
D
90 m3
3
GATE CE 2000
MCQ (Single Correct Answer)
+1
-0.3
If duty (D) is 1428 hectares/cumec and base period (B) is 120 days for an irrigated crop, then delta ($$\Delta$$) in meters is given by
A
102.8
B
0.73
C
1.38
D
0.01
4
GATE CE 2000
MCQ (Single Correct Answer)
+2
-0.6
A tube well having a capacity of 4 $$m^3 /hour$$ operates for 20 hours each day during the irrigation season. How much area can be commanded if the irrigation interval is 20 days and depth of irrigation is 7 cm?
A
$$1.71\times10^4\;m^2$$
B
$$1.14\times10^4\;m^2$$
C
$$22.9\times10^4\;m^2$$
D
$$2.29\times10^4\;m^2$$