A line balancing problem is solved in the context of
2
GATE PI 2015
Numerical
+2
-0
A manufacturing line requires $$7.2$$ minutes to make a product. The line has six workstations arranged as per the required sequence of operations. Total production required is $$300$$ products in $$7.5$$ hours. At steady state, the line efficiency, in $$\% $$, is ______________
Your input ____
3
GATE PI 2015
MCQ (Single Correct Answer)
+2
-0.6
Arrival of machines for repair in a maintenance shop follows a Poisson distribution at a rate of one per $$18$$ hours. The time to repair follows an exponential distribution with Mean Time To Repair $$(MTTR)$$ of $$14$$ hours. If the productivity loss is Rs.$$22,500$$ per hour, then the total expected loss of productivity due to machine breakdowns, in Rs., is
4
GATE PI 2015
MCQ (Single Correct Answer)
+2
-0.6
Two aluminium alloy plates each $$10$$ $$mm$$ thick and $$1$$ $$m$$ long are welded without crowning by multipass tungsten inert gas butt welding. The joint configuration is $$V$$-type with $${60^ \circ }$$ angle and root gap is maintained at $$5$$ $$mm.$$ If electrode of $$5$$ $$mm$$ diameter with $$500$$ $$mm$$ length is used for welding, then the number of electrodes required is
Paper analysis
Total Questions
Casting
2
Engineering Mathematics
8
Fluid Mechanics
1
Heat Transfer
1
Industrial Engineering
3
Joining of Materials
1
Machine Tools and Machining
10
Metal Forming
4
Metrology
2
Strength of Materials
4
Theory of Machines
1
Thermodynamics
1
More papers of GATE PI
GATE PI 2017
GATE PI 2016
GATE PI 2015
GATE PI 2014
GATE PI 2013
GATE PI 2012
GATE PI 2011
GATE PI 2010
GATE PI 2009
GATE PI 2008
GATE PI 2007
GATE PI 2006
GATE PI 2005
GATE PI 2004
GATE PI 2003
GATE PI 2002
GATE PI 2001
GATE PI 1995
GATE PI 1994
GATE PI 1993
GATE PI 1992
GATE PI 1991
GATE PI 1990
GATE PI 1989
GATE PI
Papers
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
1995
1994
1993
1992
1991
1990
1989