1
GATE PI 2015
MCQ (Single Correct Answer)
+1
-0.3
A line balancing problem is solved in the context of
A
process layout
B
Fixed position layout
C
Product layout
D
production schedule
2
GATE PI 2015
Numerical
+2
-0
A manufacturing line requires $$7.2$$ minutes to make a product. The line has six workstations arranged as per the required sequence of operations. Total production required is $$300$$ products in $$7.5$$ hours. At steady state, the line efficiency, in $$\% $$, is ______________
Your input ____
3
GATE PI 2015
MCQ (Single Correct Answer)
+2
-0.6
Arrival of machines for repair in a maintenance shop follows a Poisson distribution at a rate of one per $$18$$ hours. The time to repair follows an exponential distribution with Mean Time To Repair $$(MTTR)$$ of $$14$$ hours. If the productivity loss is Rs.$$22,500$$ per hour, then the total expected loss of productivity due to machine breakdowns, in Rs., is
A
$$78,750$$
B
$$1,01,250$$
C
$$11,81,250$$
D
$$14,17,500$$
4
GATE PI 2015
MCQ (Single Correct Answer)
+2
-0.6
Two aluminium alloy plates each $$10$$ $$mm$$ thick and $$1$$ $$m$$ long are welded without crowning by multipass tungsten inert gas butt welding. The joint configuration is $$V$$-type with $${60^ \circ }$$ angle and root gap is maintained at $$5$$ $$mm.$$ If electrode of $$5$$ $$mm$$ diameter with $$500$$ $$mm$$ length is used for welding, then the number of electrodes required is
A
$$7$$
B
$$9$$
C
$$11$$
D
$$13$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12