1
GATE PI 2015
Numerical
+2
-0
In a metal casting process, molten copper alloy is poured into a sand mould. The level of molten metal in the pouring basin is at a height of $$300$$ $$mm$$ from the runner having diameter of $$10$$ $$mm.$$ If the density and melting temperature of molten copper alloy are $$9000$$ $$kg/{m^3}$$ and $${1000^ \circ }C.$$ respectively then the rate of flow of molten metal into the mould neglecting friction and other losses, in $$c{m^3}/s,$$ is ______________.
Your input ____
2
GATE PI 2015
MCQ (Single Correct Answer)
+1
-0.3
Match the items in the first column to their functions in the second column. GATE PI 2015 Casting - Casting Process Question 10 English
A
$$P - 1,\,\,Q - 2,\,\,R - 3,\,\,S - 4$$
B
$$P - 2,\,\,Q - 4,\,\,R - 1,\,\,S - 3$$
C
$$P - 4,\,\,Q - 2,\,\,R - 1,\,\,S - 3$$
D
$$P - 2,\,\,Q - 4,\,\,R - 3,\,\,S - 1$$
3
GATE PI 2015
MCQ (Single Correct Answer)
+1
-0.3
The solution to $$\,6y{y^1} - 25x = 0\,\,$$ represents a
A
family of circles
B
family of ellipses
C
family of parabolas
D
family of hyperbolas
4
GATE PI 2015
MCQ (Single Correct Answer)
+2
-0.6
The value of $$\mathop {\lim }\limits_{\left( {x,y} \right) \to \left( {0,0} \right)} {{{x^2} - xy} \over {\sqrt x - \sqrt y }}$$ is
A
$$0$$
B
$${{1 \over 2}}$$
C
$$1$$
D
$$\infty $$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12