1
GATE PI 2015
Numerical
+2
-0
A manufacturing line requires $$7.2$$ minutes to make a product. The line has six workstations arranged as per the required sequence of operations. Total production required is $$300$$ products in $$7.5$$ hours. At steady state, the line efficiency, in $$\% $$, is ______________
Your input ____
2
GATE PI 2015
MCQ (Single Correct Answer)
+2
-0.6
Arrival of machines for repair in a maintenance shop follows a Poisson distribution at a rate of one per $$18$$ hours. The time to repair follows an exponential distribution with Mean Time To Repair $$(MTTR)$$ of $$14$$ hours. If the productivity loss is Rs.$$22,500$$ per hour, then the total expected loss of productivity due to machine breakdowns, in Rs., is
A
$$78,750$$
B
$$1,01,250$$
C
$$11,81,250$$
D
$$14,17,500$$
3
GATE PI 2015
MCQ (Single Correct Answer)
+2
-0.6
Two aluminium alloy plates each $$10$$ $$mm$$ thick and $$1$$ $$m$$ long are welded without crowning by multipass tungsten inert gas butt welding. The joint configuration is $$V$$-type with $${60^ \circ }$$ angle and root gap is maintained at $$5$$ $$mm.$$ If electrode of $$5$$ $$mm$$ diameter with $$500$$ $$mm$$ length is used for welding, then the number of electrodes required is
A
$$7$$
B
$$9$$
C
$$11$$
D
$$13$$
4
GATE PI 2015
Numerical
+2
-0
In drilling operation, a twist-drill of $$30$$ $$mm$$ diameter with point angle of $$118$$ degrees is used. If the $$CNC$$ command issued to execute the drilling operation is $$G90$$ $$G01$$ $$Z??$$ $$F20.$$ The datum is defined on the top surface of the work material and the approach distance is $$3$$ $$mm.$$ Then, to achieve a cylindrical hole depth of $$40$$ $$mm,$$ the $$Z$$ coordinate to be provided in the $$CNC$$ command, in $$mm,$$ is ______________.
Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12