1
GATE PI 2003
MCQ (Single Correct Answer)
+2
-0.6
A casting of size $$100\,\,mm \times 100\,\,mm \times 50\,\,mm$$ is required. Assume volume shrinkage of casting $$2.6\% $$. If the height of the riser is $$80$$ $$mm$$ and riser volume desired is $$4$$ times the shrinkage in casting, what is the appropriate riser diameter in $$mm?$$
A
$$14.38$$
B
$$20.34$$
C
$$28.76$$
D
$$57.52$$
2
GATE PI 2003
MCQ (Single Correct Answer)
+1
-0.3
High speed electron beam welding is focused on the weld spot using
A
vacuum lens
B
inert gas lens
C
optical lens
D
magnetic lens
3
GATE PI 2003
MCQ (Single Correct Answer)
+2
-0.6
Which of the following process can be used for welding of Aluminium alloys
$$P.$$ Submerged arc welding
$$Q.$$ Gas metal arc welding
$$R.$$ Electroslag welding
$$S.$$ Gas tungsten arc welding
A
$$P,Q$$
B
$$Q,S$$
C
$$Q,R$$
D
$$R,S$$
4
GATE PI 2003
MCQ (Single Correct Answer)
+2
-0.6
Match List - I (welding defects) with List - II (causes) and select the correct answer using the codes given below the lists GATE PI 2003 Joining of Materials - Welding Question 30 English
A
$$A - 4,\,\,B - 2,\,\,C - 3,\,\,D - 1$$
B
$$A - 4,\,\,B - 2,\,\,C - 1,\,\,D - 3$$
C
$$A - 2,\,\,B - 4,\,\,C - 1,\,\,D - 3$$
D
$$A - 2,\,\,B - 4,\,\,C - 3,\,\,D - 1$$