1
GATE PI 1991
Subjective
+5
-0
A resistance welder is rated at $$50$$ $$kVA,$$ at $$50\% $$ duty cycle. Secondary voltage is always constant at $$25$$ volts. If a job requires $$1500$$Amps current, determine the maximum welding time in a total cycle time of $$30$$$$secs$$.
2
GATE PI 1991
MCQ (Single Correct Answer)
+2
-0.6
In welding process, penetration is increased by
A
increasing current and decreasing speed
B
decreasing both current and speed
C
increasing both arc voltage and speed
D
increasing arc voltage and decreasing
3
GATE PI 1991
Fill in the Blanks
+1
-0
....................... is the non-fusion method of joining dissimilar metals with metals whose melting temp is greater than $${400^ \circ }C$$.
4
GATE PI 1991
Fill in the Blanks
+1
-0
In spot welding of aluminium sheets, the welding current should be .........A........ and weld time should be kept ............B......... than for $$MS$$ sheet of same thickness.

(A). higher / lower, (B). higher / lower

EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12