1
GATE PI 2007
MCQ (Single Correct Answer)
+2
-0.6
In a sand casting process, a sprue of $$10mm$$ base diameter and $$250mm$$ height leads to a runner which fills a cubical mold cavity of $$100mm$$ size.

The mold filling time in seconds is

A
$$2.8$$
B
$$5.78$$
C
$$7.54$$
D
$$8.41$$
2
GATE PI 2007
MCQ (Single Correct Answer)
+1
-0.3
The determinant $$\left| {\matrix{ {1 + b} & b & 1 \cr b & {1 + b} & 1 \cr 1 & {2b} & 1 \cr } } \right|$$ equals to
A
$$0$$
B
$$2b(b-1)$$
C
$$2(1-b)(1+2b)$$
D
$$3b(1+b)$$
3
GATE PI 2007
MCQ (Single Correct Answer)
+2
-0.6
Matching exercise choose the correct one out of the alternatives $$A, B, C, D$$

Group $$-$$ $${\rm I}$$
$$P.$$ $${2^{nd}}$$ order differential equations
$$Q.$$ Non-linear algebraic equations
$$R.$$ Linear algebraic equations
$$S.$$ Numerical integration

Group $$-$$ $${\rm II}$$
$$(1)$$ Runge $$-$$ Kutta method
$$(2)$$ Newton $$-$$ Raphson method
$$(3)$$ Gauss Elimination
$$(4)$$ Simpson's Rule

A
$$P - 3,\,\,Q - 2,\,\,R - 4,\,\,S - 1$$
B
$$P - 2,\,\,Q - 4,\,\,R - 3,\,\,S - 1$$
C
$$P - 1,\,\,Q - 2,\,\,R - 3,\,\,S - 4$$
D
$$P - 1,\,\,Q - 3,\,\,R - 2,\,\,S - 4$$
4
GATE PI 2007
MCQ (Single Correct Answer)
+1
-0.3
If a complex number $$z = {{\sqrt 3 } \over 2} + i{1 \over 2}$$ then z4 is
A
$$2\sqrt 2 + 2i$$
B
$$ - {1 \over 2} + i{{\sqrt 3 } \over 2}$$
C
$${{\sqrt 3 } \over 2} - i{1 \over 2}\,$$
D
$${{\sqrt 3 } \over 8} - i{1 \over 8}$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12