1
GATE PI 2011
MCQ (Single Correct Answer)
+2
-0.6
The thickness of a plate is reduced from $$30$$ $$mm$$ to $$10$$ $$mm$$ by successive cold rolling passes using identical rolls of diameter $$600$$ $$mm.$$ Assume that there is no change in width. If the coefficient of friction between the rolls and the work piece is $$0.1,$$ the minimum number of passes required is
2
GATE PI 2011
MCQ (Single Correct Answer)
+2
-0.6
In multi-pass operation, a round bar of $$10$$ $$mm$$ diameter and $$100$$ $$mm$$ length is reduced in cross-section by drawing it successively through a series of seven dies of decreasing exit diameter. During each of theses drawing operations, the reduction in cross-sectional area is $$35\% $$. The yield strength of the material is $$200$$ $$MPa.$$ Ignore strain hardening.
The total true strain applied and the final length (in $$mm$$), respectively, are
3
GATE PI 2011
MCQ (Single Correct Answer)
+2
-0.6
In multi-pass operation, a round bar of $$10$$ $$mm$$ diameter and $$100$$ $$mm$$ length is reduced in cross-section by drawing it successively through a series of seven dies of decreasing exit diameter. During each of theses drawing operations, the reduction in cross-sectional area is $$35\% $$. The yield strength of the material is $$200$$ $$MPa.$$ Ignore strain hardening.
Neglecting friction and redundant work, the force (in $$kN$$) required for drawing the bar through the first die, is
4
GATE PI 2011
MCQ (Single Correct Answer)
+2
-0.6
To measure the effective diameter of an external metric thread (included angle is $$60$$ degrees) of $$3.5$$ $$mm$$ pitch, a cylindrical standard of $$30.5$$ $$mm$$ diameter and two wires of $$2$$ $$mm$$ diameter each are used. The micrometer reading over the standard and over the wires are $$16.532$$ $$mm$$ and $$15.398$$ $$mm$$ respectively. The effective diameter (in $$mm$$) of the thread is
Paper analysis
Total Questions
Casting
3
Engineering Mathematics
7
Fluid Mechanics
1
Heat Transfer
1
Joining of Materials
2
Machine Tools and Machining
6
Metal Forming
3
Metrology
2
More papers of GATE PI
GATE PI 2017
GATE PI 2016
GATE PI 2015
GATE PI 2014
GATE PI 2013
GATE PI 2012
GATE PI 2011
GATE PI 2010
GATE PI 2009
GATE PI 2008
GATE PI 2007
GATE PI 2006
GATE PI 2005
GATE PI 2004
GATE PI 2003
GATE PI 2002
GATE PI 2001
GATE PI 1995
GATE PI 1994
GATE PI 1993
GATE PI 1992
GATE PI 1991
GATE PI 1990
GATE PI 1989
GATE PI
Papers
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
1995
1994
1993
1992
1991
1990
1989