1
GATE PI 2006
MCQ (Single Correct Answer)
+2
-0.6
Complete the manual part program for drilling a hole located at point $$(20, 20)$$ from the target point . The depth of the hole to be drilled is $$15mm$$
$$\eqalign{ & \,\,\,\,\,\,FROM/TARG \cr & \,\,\,\,\,\,GOTO/20,\,\,20,\,\,0 \cr} $$
A
$$\eqalign{ & GODLTA/0,0, - 15 \cr & GODLTA/0,0,15 \cr & GOTO/SETPT \cr} $$
B
$$\eqalign{ & GODLTA/0,0,15 \cr & GODLTA/0,0, - 15 \cr & GOTO/SETPT \cr} $$
C
$$\eqalign{ & GOTO/SETPT \cr & GODLTA/0,0, - 15 \cr & GODLTA/0,0,15 \cr} $$
D
$$\eqalign{ & GOTO/SETPT \cr & GODLTA/0,0,15 \cr & GODLTA/0,0, - 15 \cr} $$
2
GATE PI 2006
MCQ (Single Correct Answer)
+1
-0.3
In the manufacture of twist drills, the shank is joined to the body of the drill using
A
Spot welding
B
$$TIG$$ welding
C
Projection welding
D
Friction welding
3
GATE PI 2006
MCQ (Single Correct Answer)
+1
-0.3
The final finishing process for the surface plate made of cast iron which is used as a reference surface is
A
Buffing
B
Grinding
C
Hand scraping
D
honing
4
GATE PI 2006
MCQ (Single Correct Answer)
+1
-0.3
The cutting tool material normally used for turning steel of very high hardness is
A
$$HSS$$
B
tungsten carbide
C
$$CBN$$
D
diamond