1
GATE PI 2002
MCQ (Single Correct Answer)
+2
-0.6
The height of the down sprue is $$175$$ $$mm$$ and its $$CS$$ area at the base is $$200\,\,m{m^2}.$$ The $$CS$$ area of the horizontal runner is also $$200$$ $$m{m^2}$$. Assuming no losses, indicate the correct choice for the time (seconds) required to fill a mold cavity of volume $${10^6}\,\,m{m^3}.$$ (use $$g=10$$ $$m/{s^2}$$)
A
$$2.67$$
B
$$8.45$$
C
$$26.72$$
D
$$84.50$$
2
GATE PI 2002
MCQ (Single Correct Answer)
+2
-0.6
GATE PI 2002 Casting - Casting Process Question 6 English
A
$$P - 2,\,\,Q - 1,\,\,R - 3,\,\,S - 4$$
B
$$P - 1,\,\,Q - 3,\,\,R - 4,\,\,S - 2$$
C
$$P - 4,\,\,Q - 2,\,\,R - 2,\,\,S - 3$$
D
$$P - 3,\,\,Q - 4,\,\,R - 1,\,\,S - 1$$
3
GATE PI 2002
MCQ (Single Correct Answer)
+2
-0.6
A $$10$$ $$mm$$ thick steel bar is to be horizontally cast with two correctly spaced top risers of adequate feeding capacity. Assuming end effect without chill, what should be the theoretical length of the bar?
A
$$96$$ $$mm$$
B
$$132$$ $$mm$$
C
$$192$$ $$mm$$
D
$$156$$ $$mm$$
4
GATE PI 1995
Subjective
+2
-0
Match the cast defect with their cause GATE PI 1995 Casting - Casting Process Question 7 English