1
GATE PI 2007
MCQ (Single Correct Answer)
+2
-0.6
Match the following GATE PI 2007 Casting - Casting Process Question 4 English
A
$$P - 4,\,\,Q - 1,\,\,R - 3,\,\,S - 2$$
B
$$P - 2,\,\,Q - 4,\,\,R - 3,\,\,S - 1$$
C
$$P - 3,\,\,Q - 4,\,\,R - 1,\,\,S - 2$$
D
$$P - 3,\,\,Q - 2,\,\,R - 1,\,\,S - 4$$
2
GATE PI 2006
MCQ (Single Correct Answer)
+2
-0.6
A casting of size $$400mm \times 200mm \times 140mm$$ solidifies in $$20min.$$ The solidification time for a casting $$400mm \times 200mm \times 35mm$$ under similar conditions is
A
$$2min$$
B
$$3.3min$$
C
$$4min$$
D
$$8.1min$$
3
GATE PI 2005
MCQ (Single Correct Answer)
+2
-0.6
The shape factor for a casting in the form of an annular cylinder of outside diameter $$30$$ $$cm,$$ inside diameter $$20$$ $$cm$$ and height $$30$$ $$cm$$ (correction factor $$k=1.0$$) will be
A
$$21.77$$
B
$$6.28$$
C
$$9.42$$
D
$$12.28$$
4
GATE PI 2005
MCQ (Single Correct Answer)
+2
-0.6
A cast steel slab of dimension $$30 \times 20 \times 5\,\,cm$$ is poured horizontally using a side riser. The riser is cylindrical in shape with diameter and height, both equal to $$D.$$ The freezing ratio of the moulds is
A
$$8D/75$$
B
$$4D/75$$
C
$$75/8D$$
D
$$75/4D$$