1
GATE PI 2014
MCQ (Single Correct Answer)
+2
-0.6
For a given volume of a riser, if the solidification time of the molten metal in riser needs to be quadrupled, the surface area of the riser should be made
A
one- fourth
B
half
C
double
D
four times
2
GATE PI 2012
MCQ (Single Correct Answer)
+2
-0.6
A mold having dimensions $$100 \times 90 \times 20$$ (all in $$mm$$) is filled with molten metal througgh a gate with height $$'h'$$ and $$C.S$$ area $$A,$$ the mould filling time is $${t_1}$$. The height is now quadrupled and the cross sectional area is halved. The corresponding filling time is $${t_2}$$. The ratio $${t_2}/{t_1}$$ is
A
$${1 \over {\sqrt 2 }}$$
B
$$1$$
C
$${\sqrt 2 }$$
D
$$2$$
3
GATE PI 2011
MCQ (Single Correct Answer)
+2
-0.6
In a sand casting process, a sphere and a cylinder of equal volumes are separately cast from the same molten metal under identical conditions. The height and diameter of the cylinder are equal. The ratio of the solidification time of the sphere to that of the cylinder is
A
$$1.14$$
B
$$0.87$$
C
$$1.31$$
D
$$0.76$$
4
GATE PI 2010
MCQ (Single Correct Answer)
+2
-0.6
During the filling process of a given sand mould cavity by metal through a horizontal runner of circular $$C.S,$$ the frictional head loss of the molten metal in the runner will increase with the
A
Increase in runner diameter
B
Decrease internal surface roughness of the runner
C
Decrease in length of runner
D
Increase in average velocity of molten metal
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12