Critical Path Method · Construction Material and Management · GATE CE

Start Practice

Marks 1

GATE CE 2016 Set 2
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corr...

Marks 2

GATE CE 2017 Set 1
The activity details of a project are given below: The estimated minimum time (in days) for the completion of the project will be________...
GATE CE 2016 Set 2
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are...
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12