1
GATE PI 2017
Numerical
+2
-0
In a project, tasks $$A, B, C, D, E, F, G, H, I$$ and $$J$$ are to be performed. The precedence relationships and the time required (in days) to complete the tasks are given in the Table. GATE PI 2017 Industrial Engineering - Pert and Cpm Question 1 English

The time required (in days) to complete the project along the critical path is ______________

Your input ____
2
GATE PI 2017
Numerical
+2
-0
The potential production alternatives for manufacturing a product along with their unit cost and monthly capacity are given in the Table. GATE PI 2017 Industrial Engineering - Inventory Control Question 1 English

The inventory at the end of july is $$100$$ units. If the demand for the month of August is $$620,$$ then the minimum total cost (in Rs.) to meet the demand is ______________

Your input ____
3
GATE PI 2017
MCQ (Single Correct Answer)
+1
-0.3
An electrical appliances showroom sells $$2,400$$ ceiling fans in one year ($$52$$ weeks). The holding cost is $$10\% $$ of the cost of the ceiling fan. The most of one ceiling fan is Rs. $$600$$. The cost incurred for placing an order is Rs. $$201.$$ There is a lead time of $$5$$ weeks. The economic order quantity $$(EOQ)$$ and the reorder level, respectively (rounded to the next higher integer) are
A
$$231, 127$$
B
$$38, 231$$
C
$$127, 231$$
D
$$127, 13$$
4
GATE PI 2017
MCQ (Single Correct Answer)
+1
-0.3
In gas tungsten arc welding process, the material coated on pure tungsten electrode to enhance its current carrying capacity is
A
Titanium
B
Manganese
C
Radium
D
Thorium