In a project, tasks $$A, B, C, D, E, F, G, H, I$$ and $$J$$ are to be performed. The precedence relationships and the time required (in days) to complete the tasks are given in the Table. GATE PI 2017 Industrial Engineering - Pert and Cpm Question 1 English

The time required (in days) to complete the project along the critical path is ______________

Your input ____
2
GATE PI 2017
Numerical
+2
-0
The potential production alternatives for manufacturing a product along with their unit cost and monthly capacity are given in the Table. GATE PI 2017 Industrial Engineering - Inventory Control Question 1 English

The inventory at the end of july is $$100$$ units. If the demand for the month of August is $$620,$$ then the minimum total cost (in Rs.) to meet the demand is ______________

Your input ____
3
GATE PI 2017
MCQ (Single Correct Answer)
+1
-0.3
An electrical appliances showroom sells $$2,400$$ ceiling fans in one year ($$52$$ weeks). The holding cost is $$10\% $$ of the cost of the ceiling fan. The most of one ceiling fan is Rs. $$600$$. The cost incurred for placing an order is Rs. $$201.$$ There is a lead time of $$5$$ weeks. The economic order quantity $$(EOQ)$$ and the reorder level, respectively (rounded to the next higher integer) are
A
$$231, 127$$
B
$$38, 231$$
C
$$127, 231$$
D
$$127, 13$$
4
GATE PI 2017
MCQ (Single Correct Answer)
+1
-0.3
In gas tungsten arc welding process, the material coated on pure tungsten electrode to enhance its current carrying capacity is
A
Titanium
B
Manganese
C
Radium
D
Thorium
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12