1
GATE PI 2017
Numerical
+2
-0
In a project, tasks $$A, B, C, D, E, F, G, H, I$$ and $$J$$ are to be performed. The precedence relationships and the time required (in days) to complete the tasks are given in the Table.
The time required (in days) to complete the project along the critical path is ______________
Your input ____
2
GATE PI 2017
Numerical
+2
-0
The potential production alternatives for manufacturing a product along with their unit cost and monthly capacity are given in the Table.
The inventory at the end of july is $$100$$ units. If the demand for the month of August is $$620,$$ then the minimum total cost (in Rs.) to meet the demand is ______________
Your input ____
3
GATE PI 2017
MCQ (Single Correct Answer)
+1
-0.3
An electrical appliances showroom sells $$2,400$$ ceiling fans in one year ($$52$$ weeks). The holding cost is $$10\% $$ of the cost of the ceiling fan. The most of one ceiling fan is Rs. $$600$$. The cost incurred for placing an order is Rs. $$201.$$ There is a lead time of $$5$$ weeks. The economic order quantity $$(EOQ)$$ and the reorder level, respectively (rounded to the next higher integer) are
4
GATE PI 2017
MCQ (Single Correct Answer)
+1
-0.3
In gas tungsten arc welding process, the material coated on pure tungsten electrode to enhance its current carrying capacity is
Paper analysis
Total Questions
Casting
2
Fluid Mechanics
2
Heat Transfer
1
Industrial Engineering
4
Joining of Materials
1
Machine Design
2
Machine Tools and Machining
6
Metal Forming
2
Metrology
2
Strength of Materials
4
Thermodynamics
1
More papers of GATE PI
GATE PI 2017
GATE PI 2016
GATE PI 2015
GATE PI 2014
GATE PI 2013
GATE PI 2012
GATE PI 2011
GATE PI 2010
GATE PI 2009
GATE PI 2008
GATE PI 2007
GATE PI 2006
GATE PI 2005
GATE PI 2004
GATE PI 2003
GATE PI 2002
GATE PI 2001
GATE PI 1995
GATE PI 1994
GATE PI 1993
GATE PI 1992
GATE PI 1991
GATE PI 1990
GATE PI 1989
GATE PI
Papers
2017
2016
2015
2014
2013
2012
2011
2010
2009
2008
2007
2006
2005
2004
2003
2002
2001
1995
1994
1993
1992
1991
1990
1989