1
GATE PI 2005
MCQ (Single Correct Answer)
+2
-0.6
Match List - I (welding problems) with List - II (Causes) and select the correct answer using the codes given below the lists: GATE PI 2005 Joining of Materials - Welding Question 28 English
A
$$A - 2,\,B - 1,\,C - 5,\,D - 3$$
B
$$A - 3,\,B - 4,\,C - 2,\,D - 1$$
C
$$A - 2,\,B - 4,\,C - 5,\,D - 3$$
D
$$A - 3,\,B - 1,\,C - 4,\,D - 2$$
2
GATE PI 2005
MCQ (Single Correct Answer)
+2
-0.6
In a fabrication shop, a $$T$$-joint is to be made between two plates using a chain intermittent, double fillet weld of $$6$$ $$mm$$ leg length. The intermittent welds are $$40$$ $$mm$$ long and spaced $$80$$ $$mm$$ apart, edge to edge.

The welding symbol of the joint is

A
GATE PI 2005 Joining of Materials - Welding Question 1 English Option 1
B
GATE PI 2005 Joining of Materials - Welding Question 1 English Option 2
C
GATE PI 2005 Joining of Materials - Welding Question 1 English Option 3
D
GATE PI 2005 Joining of Materials - Welding Question 1 English Option 4
3
GATE PI 2003
MCQ (Single Correct Answer)
+2
-0.6
GATE PI 2003 Joining of Materials - Welding Question 31 English
A
$$P - 4,\,\,Q - 1,\,\,R - 3,\,\,S - 2$$
B
$$P - 3,\,\,Q - 2,\,\,R - 4,\,\,S - 3$$
C
$$P - 1,\,\,Q - 2,\,\,R - 4,\,\,S - 3$$
D
$$P - 2,\,\,Q - 4,\,\,R - 1,\,\,S - 3$$
4
GATE PI 2003
MCQ (Single Correct Answer)
+2
-0.6
Match List - I (welding defects) with List - II (causes) and select the correct answer using the codes given below the lists GATE PI 2003 Joining of Materials - Welding Question 30 English
A
$$A - 4,\,\,B - 2,\,\,C - 3,\,\,D - 1$$
B
$$A - 4,\,\,B - 2,\,\,C - 1,\,\,D - 3$$
C
$$A - 2,\,\,B - 4,\,\,C - 1,\,\,D - 3$$
D
$$A - 2,\,\,B - 4,\,\,C - 3,\,\,D - 1$$