1
GATE PI 2014
Numerical
+2
-0
An $$HSS$$ drill of $$20mm$$ diameter with $$5mm$$ cone height is used to drill a through hole in a steel work-piece of $$50mm$$ thickness. Cutting speed of $$10m/min$$ and feed rate of $$0.3mm/rev$$ are used. The drilling time, in seconds, neglecting the approach and over travel, is ______________
Your input ____
2
GATE PI 2013
MCQ (Single Correct Answer)
+2
-0.6
A disc of $$200$$ $$mm$$ outer and $$80$$ $$mm$$ inner diameter is faced at a feed of $$0.1$$ $$mm/rev$$ with a depth of cut of $$1$$ $$mm.$$ The facing operation is undertaken at a constant cutting speed of $$90$$ $$m/min$$ in a $$CNC$$ lathe. The main (tangential) cutting force is $$200$$ $$N$$

Assuming approach and over-travel of the cutting tool to be zero, the machining time in $$min$$ is

A
$$2.93$$
B
$$5.86$$
C
$$6.66$$
D
$$13.33$$
3
GATE PI 2013
MCQ (Single Correct Answer)
+2
-0.6
A disc of $$200$$ $$mm$$ outer and $$80$$ $$mm$$ inner diameter is faced at a feed of $$0.1$$ $$mm/rev$$ with a depth of cut of $$1$$ $$mm.$$ The facing operation is undertaken at a constant cutting speed of $$90$$ $$m/min$$ in a $$CNC$$ lathe. The main (tangential) cutting force is $$200$$ $$N$$

Neglecting the contribution of the feed force towards cutting power, the specific cutting energy in $$J/m{m^3}$$ is

A
$$0.2$$
B
$$2$$
C
$$200$$
D
$$2000$$
4
GATE PI 2012
MCQ (Single Correct Answer)
+2
-0.6
In a single pass drilling operation, a through hole of $$15$$ $$mm$$ diameter is to be drilled in a steel plate of $$50mm$$ thickness. Drill spindle speed is $$500epm,$$ feed is $$0.2mm/rev$$ and drill point angle is $${118^ \circ }.$$ Assuming $$2mm$$ clearance at approach and exit, the total drill time (in seconds) is
A
$$35.1$$
B
$$32.4$$
C
$$31.2$$
D
$$30.1$$