1
GATE PI 2016
MCQ (Single Correct Answer)
+2
-0.6
Consider a network with nodes $$1, 2, 3, 4, 5$$ and $$6.$$ The nodes are connected with directed arcs as shown in the table below. The respective costs (in $$INR$$) incurred while traversing the directed arcs are also mentioned.
The second shortest path from node $$1$$ to node $$6$$ (i.e. the path that has the second least total cost and does not use any part of the shortest path) has a total cost (in $$INR$$) of
Questions Asked from Pert and Cpm (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE PI Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Thermodynamics
Casting
Joining of Materials
Metal Forming
Machine Tools and Machining
Metrology
Industrial Engineering