1
GATE PI 2016
MCQ (Single Correct Answer)
+2
-0.6
Consider a network with nodes $$1, 2, 3, 4, 5$$ and $$6.$$ The nodes are connected with directed arcs as shown in the table below. The respective costs (in $$INR$$) incurred while traversing the directed arcs are also mentioned. GATE PI 2016 Industrial Engineering - Pert and Cpm Question 2 English

The second shortest path from node $$1$$ to node $$6$$ (i.e. the path that has the second least total cost and does not use any part of the shortest path) has a total cost (in $$INR$$) of

A
$$7$$
B
$$8$$
C
$$15$$
D
$$19$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12