1
GATE PI 2015
Numerical
+2
-0
A manufacturing line requires $$7.2$$ minutes to make a product. The line has six workstations arranged as per the required sequence of operations. Total production required is $$300$$ products in $$7.5$$ hours. At steady state, the line efficiency, in $$\% $$, is ______________
Your input ____
Questions Asked from Line Balancing (Marks 2)
Number in Brackets after Paper Indicates No. of Questions
GATE PI Subjects
Engineering Mechanics
Strength of Materials
Theory of Machines
Engineering Mathematics
Machine Design
Fluid Mechanics
Thermodynamics
Casting
Joining of Materials
Metal Forming
Machine Tools and Machining
Metrology
Industrial Engineering