1
GATE PI 2015
Numerical
+2
-0
A manufacturing line requires $$7.2$$ minutes to make a product. The line has six workstations arranged as per the required sequence of operations. Total production required is $$300$$ products in $$7.5$$ hours. At steady state, the line efficiency, in $$\% $$, is ______________
Your input ____