1
GATE PI 2003
MCQ (Single Correct Answer)
+5
-1.5
A weld is made using $$MIG$$ welding process with the following welding parameters: Current: $$200A;$$ Voltage: $$25V;$$ Welding speed: $$18$$ $$cm/min;$$ wire diameter: $$1.2$$ $$mm;$$ Wire feed rate: $$4$$ $$m/min;$$ Thermal efficiency of the process: $$65\% $$

The heat input per unit length of the weld in $$kJ/cm$$ is:

A
$$0.18$$
B
$$0.28$$
C
$$10.83$$
D
$$16.66$$
2
GATE PI 2003
MCQ (Single Correct Answer)
+5
-1.5
A weld is made using $$MIG$$ welding process with the following welding parameters: Current: $$200A;$$ Voltage: $$25V;$$ Welding speed: $$18$$ $$cm/min;$$ wire diameter: $$1.2$$ $$mm;$$ Wire feed rate: $$4$$ $$m/min;$$ Thermal efficiency of the process: $$65\% $$

The area of cross section of weld bead in $$m{m^2}$$ is:

A
$$16.3$$
B
$$25.1$$
C
$$30.3$$
D
$$38.6$$
3
GATE PI 2001
MCQ (Single Correct Answer)
+5
-1.5
A weld is made using $$MIG$$ welding process with the following welding parameters: Current: $$200A;$$ Voltage: $$25V;$$ Welding speed: $$18$$ $$cm/min;$$ wire diameter: $$1.2$$ $$mm;$$ Wire feed rate: $$4$$ $$m/min;$$ Thermal efficiency of the process: $$65\% $$

The heat input per unit length of the weld in $$kJ/cm$$ is:

A
$$0.18$$
B
$$0.28$$
C
$$10.83$$
D
$$16.66$$
4
GATE PI 2001
MCQ (Single Correct Answer)
+5
-1.5
A weld is made using $$MIG$$ welding process with the following welding parameters: Current: $$200A;$$ Voltage: $$25V;$$ Welding speed: $$18$$ $$cm/min;$$ wire diameter: $$1.2$$ $$mm;$$ Wire feed rate: $$4$$ $$m/min;$$ Thermal efficiency of the process: $$65\% $$

The area of cross section of weld bead in $$m{m^2}$$ is:

A
$$16.3$$
B
$$25.1$$
C
$$30.3$$
D
$$38.6$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12