1
GATE PI 2001
MCQ (Single Correct Answer)
+1
-0.3
Which of the following powders should be fed for effective oxy-fuel cutting of stainless steel
A
Steel
B
Aluminium
C
Copper
D
Ceramic
2
GATE PI 2001
MCQ (Single Correct Answer)
+5
-1.5
A weld is made using $$MIG$$ welding process with the following welding parameters: Current: $$200A;$$ Voltage: $$25V;$$ Welding speed: $$18$$ $$cm/min;$$ wire diameter: $$1.2$$ $$mm;$$ Wire feed rate: $$4$$ $$m/min;$$ Thermal efficiency of the process: $$65\% $$

The heat input per unit length of the weld in $$kJ/cm$$ is:

A
$$0.18$$
B
$$0.28$$
C
$$10.83$$
D
$$16.66$$
3
GATE PI 2001
MCQ (Single Correct Answer)
+5
-1.5
A weld is made using $$MIG$$ welding process with the following welding parameters: Current: $$200A;$$ Voltage: $$25V;$$ Welding speed: $$18$$ $$cm/min;$$ wire diameter: $$1.2$$ $$mm;$$ Wire feed rate: $$4$$ $$m/min;$$ Thermal efficiency of the process: $$65\% $$

The area of cross section of weld bead in $$m{m^2}$$ is:

A
$$16.3$$
B
$$25.1$$
C
$$30.3$$
D
$$38.6$$
4
GATE PI 2001
Subjective
+5
-0
In certain machining operation with a cutting speed of $$50$$ $$m/min,$$ tool life of $$45$$ minutes was observed, when the cutting speed was increased to $$100$$ $$m/min,$$ the tool life decreased to $$10$$ minutes. The cutting speed for maximum productivity, if tool change time is $$2$$ minutes is
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12