1
GATE PI 1992
Subjective
+2
-0
Match the application with type of pattern GATE PI 1992 Casting - Casting Process Question 9 English
2
GATE PI 1992
MCQ (Single Correct Answer)
+1
-0.3
The primary function of a riser is to
A
feed molten metal to casting as it solidifies
B
prevent atmospheric air from contaminating the metal in the mold
C
allow gases to easily escape from mold cavity
D
allow molten metal to rise above the mold cavity
3
GATE PI 1992
Subjective
+5
-0
Two sheets of low carbon steel $$1.5mm$$ thick each are spot welded by passing a current $$10000$$ amps for $$5$$ cycles in $$50$$ $$Hz$$ main supply.

i) What is the heat generated due to the supply of power if effective resistance has $$200$$ micro ohms,

ii) The maximum indentation is $$10\% $$ of sheet thickness and density of the spot weld nugget $$8$$ $$gm/cc.$$ If $$1380$$ Joules are required to melt $$1gm$$ of steel, determine heat required for welding operation if $$D=6SQRT$$ $$(t)$$ to determine nugget diameter $$D$$ and assume the nugget size to be equal to metal between the two electrodes

4
GATE PI 1992
MCQ (Single Correct Answer)
+1
-0.3
The type of coated electrode most widely used for welding low carbon steel is
A
cellulose
B
acidic
C
rutile
D
oxide