X , Y and Z can complete a work in 5 days, 15 days and 30 days, respectively. In how days can the work be completed if X is assisted by Y and Z together, on every second day?
1
5 days
2
4 days
3
7 days
4
6 days
2
SSC CGL Tier I - 26th July 2023 Shift 3
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Abraham can complete a work in 9 days, while Andrew can complete the same work in 6 days. In how many days can they complete the work if they work together?
1
2
2
$3{3 \over 5}$
3
$2{3 \over 5}$
4
3
3
SSC CGL Tier I - 26th July 2023 Shift 3
MCQ (Single Correct Answer)
+2
-0.5
Change Language
A, B and C can finish a work in 15 days working alternately in the same order. The efficiency of A is the same as that of B, and the efficiency of C is equal to that of A. In how many days will the work be finished if they work alternately in the order C, A and B?
1
12
2
14
3
15
4
16
4
SSC CGL Tier I - 26th July 2023 Shift 4
MCQ (Single Correct Answer)
+2
-0.5
Change Language
15 men complete a work in 10 days. 15 women complete the same work in 12 days. If all these men and women work together, then the number of days required to complete that work is:
1
$5 \frac{5}{11}$
2
$4 \frac{3}{11}$
3
$7 \frac{2}{11}$
4
$6 \frac{4}{11}$