X , Y and Z can complete a work in 5 days, 15 days and 30 days, respectively. In how days can the work be completed if X is assisted by Y and Z together, on every second day?
1
5 days
2
4 days
3
7 days
4
6 days
2
SSC CGL Tier I - 26th July 2023 Shift 3
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Abraham can complete a work in 9 days, while Andrew can complete the same work in 6 days. In how many days can they complete the work if they work together?
1
2
2
$3{3 \over 5}$
3
$2{3 \over 5}$
4
3
3
SSC CGL Tier I - 26th July 2023 Shift 3
MCQ (Single Correct Answer)
+2
-0.5
Change Language
A, B and C can finish a work in 15 days working alternately in the same order. The efficiency of A is the same as that of B, and the efficiency of C is equal to that of A. In how many days will the work be finished if they work alternately in the order C, A and B?
1
12
2
14
3
15
4
16
4
SSC CGL Tier I - 26th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Pipe A and pipe B running together can fill a cistern in 6 minutes. If B takes 5 minutes more than A to fill it, then the time in which A and B will fill that cistern separately will be, respectively, __________ .
1
15 min and 10 min
2
15 min and 20 min
3
25 min and 20 min
4
10 min and 15 min