SSC CGL Tier I - 26th July 2023 Shift 4
MCQ (Single Correct Answer)
+2
-0.5
Change Language
15 men complete a work in 10 days. 15 women complete the same work in 12 days. If all these men and women work together, then the number of days required to complete that work is:
1
$5 \frac{5}{11}$
2
$4 \frac{3}{11}$
3
$7 \frac{2}{11}$
4
$6 \frac{4}{11}$
2
SSC CGL Tier I - 26th July 2023 Shift 4
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Ramesh alone can complete a work in 24 days. Ramesh and Somesh can complete it in 8 days. How long will Somesh alone take to complete the work?
1
10 days
2
15 days
3
14 days
4
12 days
3
SSC CGL Tier I - 26th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Pipe A and pipe B running together can fill a cistern in 6 minutes. If B takes 5 minutes more than A to fill it, then the time in which A and B will fill that cistern separately will be, respectively, __________ .
1
15 min and 10 min
2
15 min and 20 min
3
25 min and 20 min
4
10 min and 15 min
4
SSC CGL Tier I - 26th July 2023 Shift 2
MCQ (Single Correct Answer)
+2
-0.5
Change Language
Pipe A can fill 50% of the tank in 6 hours and pipe B can completely fill the same tank in 18 hours. If both the pipes are opened at the same time, in how much time (in minutes) will the empty tank be completely filled?
1
420
2
425
3
432
4
435