4 men’s work is equal to 6 women’s work, and 4 women’s work is equal to 6 boys’ work. A boy can finish the work in 60 days. In how many days can the work be finished by a man and a woman together?
1
16
2
24
3
20
4
12
2
SSC CGL Tier I - 26th July 2023 Shift 1
MCQ (Single Correct Answer)
+2
-0.5
Change Language
A group of men decided to do a job in 11 days but 16 men left the work after each day. The work, as a result, got completed in 15 days. How many men were there initially in the group?
1
400
2
480
3
420
4
450